Compensation delayed for aggrieved homebuyers in Karnataka

Hundreds of homebuyers in Karnataka have been left in the lurch as they still haven’t received compensation from the developers. The Karnataka RERA has already passed orders against these errant developers and penalized them for not delivering possession

Filing of insolvency petition before NCLT by the Homebuyer- A Complete Analysis

In the year of 2016, a new set of laws as RERA Act have been implemented, specifically to protect the homebuyer and ensure the growth of real estate sector.

Can homebuyer approach NCLT before RERA?

RERA has been specifically setup to regulate the real estate sector therefore one must approach RERA before approaching NCLT.

Builders not liable to pay for ‘justified’ delays: MahaRERA

MUMBAI: The Maharashtra Real Estate Regulatory Authority has for the first time expanded the scope of reasons beyond a builder’s control. The authority upheld a city builder’s claim that a 2009 project was delayed due to change of law, administrative conflicts and “incorrect classification of the plot as CRZ II’’ —reasons beyond his control. Hence, the builder … Continue reading “Builders not liable to pay for ‘justified’ delays: MahaRERA”

Incorporation of One-Sided Clauses in an Agreement Constitutes Unfair Trade Practices: NCDRC

Incorporation of one-sided clauses in the agreement where the buyer is expected to sign on the dotted lines having no other option would amount to unfair trade practices under the Consumer Protection Act, 1986.

Consumer court have the power to direct refund and compensation in case of delayed delivery of the apartment

The Consumer Protection Act is a wide-ranging provision and it is not a specific resolution like the Insolvency ad Bankruptcy Code and the remedies are simultaneously and mutually exclusive.

Limitation is continuous in cases of Homebuyers

If a homebuyer failed to file his/her case then will his/her case will not be taken and his grievances won’t be solved? The answer to this question is “NO”! The reason here is that the limitation period in the case of a homebuyer is continuous in view of the non-handing over of the possession of the unit.

Rights and Duties of the Allottees

Neither the promoter nor the allottee can deny such rights & duties as mentioned in this article no matter what has been documented by the Builder or agreed by the Allottee.

How to claim interest on Delayed Project

RERA Act grants the remedy to the homebuyers where they can file a complaint under section 31 of RERA Act and can claim interest for delay in possession by the developers. Homebuyers must seek legal assistance without delaying.

Legel remedies to get refund on stalled projects: An Analysis

Section 18(1) of the RERA Act provides for ‘Return of amount and compensation’ which is the base for complaint under section 31 seeking refund, interest and compensation.