Interest for Delayed Period of Possession to be calculated from date of default of Handing over Possession

The promoter is under obligation to pay interest on the amount paid by allottee from the date of payment till the possession is handed over to allottee.

Land Allotment Cancellation over Non-Payment of Dues, Red Alert for the Developers

the Yamuna Expressway Industrial Development Authority had cancelled the allotment of ‘Panorama’ in Sector 22A over non-payment of dues of Rs 46.8 crore.

Builders forcing to take possession without Occupancy Certificate

A customer should remember of taking each document from the builder. The occupancy certificate should be taken before creating the ultimate possession payment to the builder to avoid any downside in future.

Recovery can be permitted against the assets of group companies: Bombay High Court

If the non-payment of a clear undisputed amount is being illegally and dishonestly avoided, whilst at the same time very large sums of money are being raised and spent by the same group or carrying on large real estate development projects.

MahaRERA orders CCI Projects to Pay Interest on Delayed Possession

The MahaRERA in three separate orders directed the CCI Projects Ltd to pay interest on delayed period of possession after the ongoing six-month moratorium due to covid-19 crisis is over.

NBCC to handover 27,223 houses of Amrapali Group soon

Out of the total 45,000 houses in the stalled projects of Amrapali Group, the process of completion of about 40000 housing units has begun. A huge relief to the homebuyers.

Corporate Debtor cannot be blamed for delay in delivery of possession when delay occurs due to Force Majeure

Whether the delay in delivering possession is due to the Corporate Debtor & in case the delay is not due to the Corporate Debtor, but force majeure, it cannot be alleged that the Corporate Debtor has defaulted in delivering the possession.

Consumer Forums back in the game-orders full refund in case of Delayed Possession

Chandigarh consumer commission coming to the rescue of the homebuyers has been able to restore its faith among homebuyers.

MAHARERA: Auction of the Property to recover the Money of allottees’

Maha-RERA issued a revenue recovery warrant and sent it to the Thane collector. And was forward to the Tehsildar of the area for property sealing and auctioning to recover the money.

Remedies for misappropriation of Interest Free Maintenance Security Charges

IFMS is an additional amount given by the buyers to the developer/builder till the time resident’s welfare association (RWA) is formed. The purpose of forming RWA is maintenance purpose, security purpose and projects for developments.

One-sided terms in favor of Builder are non-enforceable: Supreme Court

The Supreme Court has finally settled the law and has provided relief to all the allottees which were being regularly harassed by the builders under the shed of one sided clauses in the Apartment Buyer’s Agreements.

Best Legal remedy for Stalled Real Estate Project – A Comparison

More than 5 Lakh homebuyers are struck in the projects which are either stalled for multiple years or has been abandoned. The builder either don’t have money or intention to start construction on such products.

MREAT allowed delay of 14 months and 22 days to allottees

In the matter of Mr. Anil Mnagaldas Vade & ors. vs. Siddhitech Developers, the delay in filing an appeal u/s 44 of RERA Act, MREAT allowed delay of 14 months & 22 days to homebuyers.

Are you a promoter puzzled with MahaRERA Compliances?

MahaRERA has been a model for other states. Recently, its proved again when suo motu action was taken for the first time against large group of promoters.