After the registration of the project if any defect comes into light which creates any problem in completion of the project, RERA Act provides remedy for the same.
Legel remedies to get refund on stalled projects: An Analysis
Section 18(1) of the RERA Act provides for ‘Return of amount and compensation’ which is the base for complaint under section 31 seeking refund, interest and compensation.
Subvention Scheme: A Crisis for Homebuyers
A subvention scheme may end up to be a double-barreled if the developer fails to deliver the project on time, the burden of both rent and EMI will must be borne by the homebuyer.
How RERA and NCLT would be a solution for stuck projects
Different forums provide for different reliefs and one must be cautious enough before choosing an appropriate forum. Before choosing the appropriate forum, points to be analyzed are type of violation by the builder, what relief is prayed for, urgency, repetitive nature, financial condition of the builder, status of other projects, etc.
Haryana Government attached builder’s land for violating provisions of environment act
The Haryana State Pollution Control Board (hereinafter referred to as HSPCB) directed Rs. 45.40 crore penalty for violation of the Environment Act provisions. Additionally, the government has proceeded with criminal prosecution against delinquent builder in the environment court of Kurukshetra.
EVEN AFTER POSSESSION, NO SIGN OF OC FOR UNITECH ESCAPE RESIDENTS
It’s overthree years, around 30 families got possession in one of the eight towers in the Unitech Escape on Golf Course Road (extension) but still didn’t get an occupation certificate.
Thousands of acres of land hitherto not utilized by Bangalore Development Authority
a senior Bangalore DEvelopment Authority official stated that some properties are encroached, while some other are trapped under the litigation process.
Reply to Legal Notice under Section 13(2) of SARFAESI Act, 2002 Pertaining to Subvention Scheme
The banks are aware of the builder’s liability to make all the payments to the bank according to the signed agreement among the bank, builder, and buyer. Therefore, the banks cannot chase or harass the buyers for payment of due amounts under the SARFASI Act, 2002.
Legal solutions when real estate project is stuck
Since the real estate projects are the turkey projects and take multiple years to get it completed, a normal delay can be accepted. Any delay of more than 1 year from promised date of possession is regarded as ‘extra-ordinary delay’.
Insolvency and Bankruptcy Code (Amendment) Bill, 2021
The Code was enacted in 2016 to consolidate and amend the laws governing corporate reorganization and insolvency resolution for corporations, partnerships, and individuals.
Recovery can be permitted against the assets of group companies: Bombay High Court
If the non-payment of a clear undisputed amount is being illegally and dishonestly avoided, whilst at the same time very large sums of money are being raised and spent by the same group or carrying on large real estate development projects.
Invocation of a bank guarantee during a moratorium period imposed under the IBC is allowed
The NCLAT ruling, on the other hand, may present some difficulties for banks that have extended bank guarantees. When the IBC imposes a moratorium period, recouping funds paid under bank guarantees from a corporate debtor may be difficult.
Status of claims that do not form part of the Resolution Plan
Claims that do not form part of the resolution plan will be extinguished on the date of the adjudicating authority’s acceptance of the resolution plan. This ruling has reaffirmed the IBC’s goal, which is for the Corporate Debtor to start over with a clean slate based on the resolution plan.
AA has limited power of judicial review if resolution plan is approved by CoC: SC
Supreme Court’s decision in Maharashtra Seamless Limited shows that the commercial wisdom of the CoC will be given top priority when deciding on the feasibility and viability of the resolution plan.
CoC is empowered to consider revised financial offers keeping in mind the time limit set out by law: NCLAT
The NCLAT had to decide whether the NCLT/CoC may provide resolution applicants repeated chances to alter their individual resolution plans and whether the CoC was authorised to entertain fresh or revised resolution plans without exhausting available bids.