RERA: Is refund the only solution for the aggrieved homebuyers?
The RERA authorities of the Various State are not granting refund looking into the wider interest of the Real Estate Sector.
The RERA authorities of the Various State are not granting refund looking into the wider interest of the Real Estate Sector.
The execution of the orders is still a far fetched process as the RERA has failed to implement the execution mechanism under the RERA.
In case the government issues the notification of superseding the Authority it shall give a reasonable opportunity to the Authority to make representations against the notification.
Approaching RERA has been rightly helpful for the homebuyers who have not received the possession or refund of the amount paid by them to the builders or developers.
In many complaints, the builder contends that “Interest” is in the nature of compensation and it has to be decided by the Adjudicating officer and RERA Authority does not have any jurisdiction related to the decision of granting interest.
RERA Authority of Gurgaon has given the way out in the matter and finally, the home-buyers of the project can expect some results on the ground.
Real estate across the country is already witnessing signs of revival. In the last couple of quarters in this financial year, sales have witnessed more than 20% improvement over last year.
As per the RERA laws, no civil court has the jurisdiction to entertain any suit or proceedings which is empowered to be entertained RERA Authority only.
The RERA ordered the builder to refund the entire principal amount along with interest of 15% per annum to be compounded quarterly from the dates of deposit to the date of refund should be refunded in three instalments by the company
The matter of Shubhkamna in Greater Noida wherein the Authority has asked for a plan for the association of buyers to facilitate the complete works of the remaining project.
The delay in projects got converted from months to years shattering the dream of owning a home of many homebuyers. A detailed article on how to get refund from the builders under RERA.
UP RERA recently took a massive step by issuing recovery notice against 5 builders who failed to abide by the orders made by the Authority.
UP RERA recently took a massive step by issuing recovery notice against 5 builders who failed to abide by the orders made by the Authority.
RERA Authority order is not being complied with by the party or if we are precise, the builder is not paying the amount ordered by authority.
Some of the legal remedies available for the homebuyers of stalled real estate projects against builders in case of disputes or grievances. Homebuyers can protect themselves from builders in India and ensure that they get their dream home without any hassles.