MahaRERA Orders Refund as Project Failed to Receive CC

In a landmark order, the MAHARERA has gone a step ahead in safe guarding the rights of the Homebuyer’s and allowed refund when the developer could not get the Completion Certificate. This will help the buyers protect their money in cases where project is sold and developer fails to get the basic certificates for construction.

MahaRERA orders for Refund – Strikes down a Forfeiture clause as unjust and Deceitful

A milestone judgement by the MahaRERA Authority to ensure the development of the real estate industry by protecting the homebuyer’s interest by balancing the rights of homebuyers as well as project developers.

UPRERA imposed penalty of Rs. 1.6 cr while deregistering two Ansal API projects

Strict action has been taken as two projects of Ansal API has been de-registered by the UPRERA Authority after the promoter could not provide a satisfactory response to the notices sent by the Authority.

RERA Imposes Rs 2.5 Crs penalty on developers for failure to comply the RERA orders

UPRERA Authority has imposed penalty of Rs 2.5 crore against 11 developers for failing to comply with the authority’s order, which were in favor of homebuyers.

Punjab & Haryana HC Finally settles the Dispute of Power between RERA Authority and Adjudicating Officer

The High Court of Punjab and Haryana finally settles the dispute of granting refund under RERA. The High Court in a detailed judgment has finally decided the matter in favour of RERA Authority and has ruled that RERA Authority will have power to grant refund and possession and Adjudicating officer will only have limited power with respect to granting Compensation.

What are Rehabilitation Scheme for Stalled Projects under UP RERA

One of a kind orders that transformed a stalled project into a Rehabilitation project under Section 8 of the RERA.

A Welcome Step by UPRERA – Makes way for homebuyers aggrieved of Conciliation Agreement

Conciliation forum is one such mechanism to resolve the issues adeptly. But there are several cases in which a conciliation agreement has not been honored by the builders.

Compliance of Recovery Certificate (RC) issued by RERA in Uttar Pradesh

An allottee can write a representation addressed to the DM explaining his grievance and praying for the compliance of the RC issued by the RERA within a specified period of time.

Homebuyer with refund order is financial creditor, not a homebuyer any more

The homebuyers who have got RERA refund orders and if builder has defaulted in making the payment, you can file case before NCLT under IBC laws

Builders request for setting aside of Refund and Penalty Orders: Is it possible?

Builders requested that Refund and penal orders to be set aside or be reviewed due to the COVID-19 outbreak financial markets are seeing an all-time low.