MUMBAI: The Maharashtra Real Estate Regulatory Authority has for the first time expanded the scope of reasons beyond a builder’s control. The authority upheld a city builder’s claim that a 2009 project was delayed due to change of law, administrative conflicts and “incorrect classification of the plot as CRZ II’’ —reasons beyond his control. Hence, the builder … Continue reading “Builders not liable to pay for ‘justified’ delays: MahaRERA”

Wait! Till 31st July for RERA Compliant Homes

There is a large chunk of unsold inventory across the locations and available with almost all the builders. They would in all likelihood be trying to offload them and even offer a reduced rate along with other freebies. Buyers showing renewed interest in this market have to be cautious as the chances of falling into a trap could be high.